Gas, Plumbing and Electrical Permits
Source: IJD Inspections Ltd.
Gas Permit Applications
In order to issue a gas permit, the applicant must submit:
- Completed permit application
- Method of payment
Gas Permit Application Form
Eligibility
- For a single-family dwelling, the applicant may be the owner and occupant of the property or may be a Certified Gas Contractor.
Site Inspection Stages
- Final Inspection: Project is complete
Please provide 48 hours notice to arrange for the necessary inspections.
Plumbing Permit Applications
In order to issue a plumbing permit, the applicant must submit:
- Completed permit application
- Method of payment
Plumbing Permit Application Form
Eligibility
- For a single-family dwelling, the applicant may be the owner and occupant of the property or may be a Certified Plumbing Contractor.
Typical Site Inspection Stages
- Rough-in Below Grade Inspection: Prior to covering
- Rough-in Above Grade Inspection: Prior to covering
- Final Inspection: Project is complete
Please provide 48 hours notice to arrange for the necessary inspections.
Electrical Permit Applications
In order to issue an electrical permit, the applicant must submit:
- Completed permit application
- Method of payment
Eligibility
- For a single-family dwelling, the applicant may be the owner and occupant of the property or may be a contractor who holds a Master Electrician Certificate. Service must be 100 amps or less for a home-owner permit.
Typical Site Inspection Stages
- Rough-in Inspection: Prior to covering
- Final Inspection: Project is complete
Please provide 48 hours notice to arrange for the necessary inspections.
Inspection Stages
1 .Rough-in Inspection
- Meter base, service panel, service conductors and grounding must be installed.
- All outlet boxes are to be mounted and secured in such a manner that they will be flush with finished walls and ceilings.
- All wiring installation in outlet boxes and splices must be completed.
- All ground wires are to be attached to the outlet boxes and spliced as required.
2. Final Inspection
- All wiring devices (switch, receptacles, fixtures, and wall plates) installed.
- All branch circuits wiring to be installed in panel and connected to the circuit breakers.
- Panel directory to be properly labeled.
- Gas and water lines to be bonded to ground.
|